A request that misses Monday noon waits for the following week's board
Papers close on Monday at noon for a Thursday meeting, so a request raised on a Tuesday waits nine days to be seen and one raised on Monday morning waits three. One requester now plans three weeks for a change that the operations lead says can take twenty minutes in the window.
“I submitted it on the Tuesday after papers had closed, so it missed that week's board.”Application developer, 5 years in role
Show all 4 quotes and their conversations
-
“I submitted it on the Tuesday after papers had closed, so it missed that week's board.”
Application developer, 5 years in role
Open the conversation
LontraThink of the last change you raised. What happened between submitting it and it going live?
Application developerA one-line configuration change on the document upload service. Twenty minutes of actual work. I submitted it in early June and it went live on 9 July.
LontraWhere did the time go?
Application developerI submitted it on the Tuesday after papers had closed, so it missed that week's board. The week after, it was sent back: rollback plan missing. I'd put 'revert the setting' and apparently that isn't a rollback plan. Then I resubmitted and it needed security.
LontraThe history you shared shows the security review was requested on 23 June, thirteen days after you submitted. Did you know it would be needed?
Application developerNo. The form doesn't ask whether it touches personal data. I found out when security emailed me.
LontraHow do you fill in the form?
Application developerI copy my last one and change the bits. It's thirty-eight fields. The board reads four of them, I'm told.
LontraHow do you know where your request is?
Application developerI don't. It says Submitted until it says Approved. I email the admin.
LontraHow many changes do you raise?
Application developerTwo or three a month.
LontraWhat would you change first?
Application developerShow me the status. And ask the security question on the form, so I find out on day one, not day thirteen.
-
“A week. Two if I miss Monday.”
Infrastructure engineer, 10 years in role
Open the conversation
LontraHow often do you raise changes?
Infrastructure engineerWeekly. Network and servers.
LontraHow long do they take to get approved?
Infrastructure engineerDepends. A week. Two if I miss Monday.
LontraWhat do you do when it can't wait?
Infrastructure engineerEmergency. Same day, usually.
LontraHow do you know where a request is?
Infrastructure engineerI don't. Email the admin.
LontraIs there anything else you'd want the board to know?
Infrastructure engineerNo. It's the process.
-
“I plan for three weeks now. I used to plan for one.”
Project manager, business side, 2 years in role
Open the conversation
LontraWhat changes do you raise, and what was the first one like?
Project managerReleases for my project. I'm not technical. The first time I filled the form in it came back the following week for the rollback plan. I'd no idea what a rollback plan was. I rang a developer to write it for me.
LontraHow long do you plan between deciding a release date and having approval?
Project managerI plan for three weeks now. I used to plan for one.
LontraWhat changed?
Project managerI learned. Papers close Monday at noon. Anything after that is next week. And I know I'll probably be sent back once, so I submit two weeks ahead, not one.
LontraDoes security come into it?
Project managerOnly if the board asks. For my last release they asked on the Thursday and then security took five days. I'd have gone to security first if I'd known. Nobody told me.
LontraHow do you know where your request is?
Project managerI look at the agenda the admin sends on Tuesday night. If I'm not on it, I'm waiting.
LontraWhat would you change?
Project managerTell me up front what a request needs. A checklist.
-
“Submit on a Tuesday, nine days. Submit on a Monday morning, three.”
Change administrator, 4 years in role
Open the conversation
LontraWhat does a normal week look like for you?
Change administratorPapers close Monday at noon. Monday afternoon I build the pack, Tuesday night it goes out with the agenda, Thursday is the board, Friday I send the outcomes. In between I'm answering emails. About twenty-five a week. Where's my change?
LontraWhat are they asking?
Change administratorMostly has it been seen, am I on Thursday's agenda, why was it sent back.
LontraHow long does a request take from submission to approval?
Change administratorSubmit on a Tuesday, nine days. Submit on a Monday morning, three. That's if it's approved first time.
LontraThe log you shared shows 87 requests heard over six boards, and 30 of them returned for information. What happens to those 30?
Change administratorThey go on the next agenda once they're resubmitted, if the missing piece is in by Monday noon. Mostly it isn't, first time, so it's another week or two. It's usually the rollback plan. Sometimes the test evidence.
LontraAnd when security is involved?
Change administratorSecurity only comes in after the board has asked, so for those changes it's two cycles.
LontraHow does the emergency route work?
Change administratorTwo board members sign it off by email, same day. It's meant for outages. I log them, and it's more than it should be if it's only for outages.
LontraIf you could change one thing, what would it be?
Change administratorLet people see where their request is. A status field. I'd stop answering half of those emails. And it's not one thing. It's the Monday cut-off, the send-backs and the second look all stacking up.